IT-Zertifizierung PMI PMI-002
Access Routing and LAN Switching;Advanced Routing and Switching;APE;APE for Validating Knowledge;Architecture;
CCDA;CCDE; CCDP;CCENT;CCIE;CCIE Data Center;CCIP; CCNA;
CCNA Security;CCNA Wireless;CCNA Voice;CCNP;CCNP Data Center
;CCNP Service Provider; CCNP Wireless;CCNP Security;CCNP SP Operations; CCNP Voice;CCSP;CCVP;Cisco Express Foundation Field Specialist;Cisco Security Sales Specialist;Cisco Specialist;Cisco Virtual Classroom;Connected Grid;Content Networking;Data-Center;Field Technician;IP Communications;IronPort; Network Management; Optical;Others
;Proctored Exams for Validating Knowledge;Sales Expert; Security Specialist;Service Provider Video;SMB;SP Video
;Storage Networking; Substation Automation;TelePresence Video
;Unified Communications;VPN and Security; WAASSE; Wireless LAN
PMI-002 Certified Associate in Project Management (CAPM) Certification Der einfachste Weg für die IT-Prüfung vorzubereiten, ist die Praxis-Tests auf Zertifizierungsprüfung Muster zu nehmen und zu verstehen, die richtige sowie falsche Antwort Erklärungen Deine Zweifel klären. Lesen Sie dazu auch relevante technische Artikel zu versierter in der damit verbundenen Technologie.
IT-Zertifizierung PMI PMI-002
QUESTION NO: 1
A contract cannot contain _____________.
A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above
Answer: A
Explanation:
A contract cannot contain illegal activities. A contract can contain other options available.
QUESTION NO: 2
Which one of the following comes first in the project plan?
A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan
Answer: A
Explanation:
Scope statement comes first in the project plan. Scope statement is the written statement of project. It contains: Project objectives, Project justification, Project deliverables
QUESTION NO: 3
You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn’t have the manufacturing capability. This is an example of which selection tool?
A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment
Answer: B
Explanation:
A screening system rejects sellers that does not meet minimum requirements for the project.
QUESTION NO: 4
______________ provides details about how the project scope may be changed.
A. Control Scope system
B. VeiirV Scope
C. Scope Charter
D. Scope Management plan
Answer: D