IT-Zertifizierung Oracle 1Z0-567
Access Routing and LAN Switching;Advanced Routing and Switching;APE;APE for Validating Knowledge;Architecture;
CCDA;CCDE; CCDP;CCENT;CCIE;CCIE Data Center;CCIP; CCNA;
CCNA Security;CCNA Wireless;CCNA Voice;CCNP;CCNP Data Center
;CCNP Service Provider; CCNP Wireless;CCNP Security;CCNP SP Operations; CCNP Voice;CCSP;CCVP;Cisco Express Foundation Field Specialist;Cisco Security Sales Specialist;Cisco Specialist;Cisco Virtual Classroom;Connected Grid;Content Networking;Data-Center;Field Technician;IP Communications;IronPort; Network Management; Optical;Others
;Proctored Exams for Validating Knowledge;Sales Expert; Security Specialist;Service Provider Video;SMB;SP Video
;Storage Networking; Substation Automation;TelePresence Video
;Unified Communications;VPN and Security; WAASSE; Wireless LAN
1Z0-567 Primavera P6 Enterprise Project Portfolio Management 8 Essentials Exam Der einfachste Weg für die IT-Prüfung vorzubereiten, ist die Praxis-Tests auf Zertifizierungsprüfung Muster zu nehmen und zu verstehen, die richtige sowie falsche Antwort Erklärungen Deine Zweifel klären. Lesen Sie dazu auch relevante technische Artikel zu versierter in der damit verbundenen Technologie.
IT-Zertifizierung Oracle 1Z0-567
QUESTION NO: 1
You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?
A. Your security does not allow you to update Activity Status.
B. You did not save the changes made to the activities.
C. You have not completed each of the activity steps.
D. You must refresh the view in the web to view the changes.
Answer: B
QUESTION NO: 2
You are creating a new portfolio scenario. You are attempting to save it for all users, but the selection is unavailable (grayed out).
What is the cause?
A. You have insufficient global security privileges.
B. You have Insufficient project security privileges.
C. You have insufficient portfolio security privileges.
D. You have insufficient user security privileges.
Answer: A
Explanation: Global profiles:
Define a user’s access to application-wide information and settings, such as the enterprise project structure (EPS), resources, roles, and cost accounts. Each user must be assigned a global profile.
QUESTION NO: 3
Your customer wants to take advantage of capacity planning in portfolios. The customer would like to use generic resources, because they have greater flexibility to respond to changing costs by resource by location. In fact, they would prefer not to set up any roles at all in the database, because they perceive generic resources and roles to be duplicate effort. What would an appropriate response be to this customer?
A. Use generic resources in Capacity Planning view, because they have greater ability to respond to changing costs.
B. User generic resources for project financials, and mirrored roles for capacity planning.
C. Use roles for planning and project financials to eliminate duplicate data maintenance.
D. Integrate with HR systems to obtain automated generic resource pricing updates.
Answer: B
IT-Zertifizierung Oracle 1Z0-567