IT-Zertifizierung PMI CA0-001

IT-Zertifizierung PMI CA0-001

Access Routing and LAN Switching;Advanced Routing and Switching;APE;APE for Validating Knowledge;Architecture;
CCDA;CCDE; CCDP;CCENT;CCIE;CCIE Data Center;CCIP; CCNA;
CCNA Security;CCNA Wireless;CCNA Voice;CCNP;CCNP Data Center
;CCNP Service Provider; CCNP Wireless;CCNP Security;CCNP SP Operations; CCNP Voice;CCSP;CCVP;Cisco Express Foundation Field Specialist;Cisco Security Sales Specialist;Cisco Specialist;Cisco Virtual Classroom;Connected Grid;Content Networking;Data-Center;Field Technician;IP Communications;IronPort; Network Management; Optical;Others
;Proctored Exams for Validating Knowledge;Sales Expert; Security Specialist;Service Provider Video;SMB;SP Video
;Storage Networking; Substation Automation;TelePresence Video
;Unified Communications;VPN and Security; WAASSE; Wireless LAN

CA0-001 Certified Associate in Project Management Der einfachste Weg für die IT-Prüfung vorzubereiten, ist die Praxis-Tests auf Zertifizierungsprüfung Muster zu nehmen und zu verstehen, die richtige sowie falsche Antwort Erklärungen Deine Zweifel klären. Lesen Sie dazu auch relevante technische Artikel zu versierter in der damit verbundenen Technologie.

IT-Zertifizierung PMI CA0-001

QUESTION NO: 1
The work breakdown structure is ________.

A. Used to break down the project into manageable pieces
B. Set and does not change throughout the project
C. Needed as part of the project charter
D. [Needed as part of the project scope statement

Answer: A

Explanation:
Work Breakdown Structure (WBS): A deliverable-oriented grouping of project elements which organizes and defines the total scope of the project. It sub divide the major tasks to minor details.

QUESTION NO: 2
If a project with a SPI of 1.8, what you tell?

A. The project is running ahead of the schedule
B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None

Answer: A

Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule
performance index of 1 or greater suggests that the project is ahead of schedule.

QUESTION NO: 3
You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?

A. Pi’ojectized
B. Strong Matrix
C. Weak Matrix
D. Functional

Answer: B

Explanation:
Projectized Organization: Any organizational structure in which the project manager has full authority to assign priorities and to direct the work of individuals assigned to the project. Strong Matrix: The project manager is assigned full time and has a full time support staff. Project manager has the preeminent position of authority. Weak Matrix: Power reset with Functional Manager.
Functional: In this organization Project Manager has least power and all management is taken care by functional manager like marketing engineer, sales engineer.